PM*** F5 December 2014 Exam was.. Instant Poll and comments ***
@emo777 said: Everyone, post your answers on high low52x high low
And the about abc
Cots driver changes the activity
Traditional absorption under locates
I think both options were correct right??
Yeah I think high low was 52x
As this was the VC
I actually calculated FC too which was there in front of it 16something
Traditional absorption cost - over absorpt overhead in high volume product
under - was wrong
Great!
And what about the strategic planning on existing resource
And operation on existing task
Was info about strategic planning incorrect? Only operations was correct
Strategic was finding new resource right as the planning would use existing resource and operational would be for specific task
Strategic was incorrect
I think both are incorrect about strateguc and operational both are reverse
I think I done the same.
Strategic wrong and operation correct
Ahsan I think operation was right. Coz if yiu think operation than its day to day activity which means a specific task
In strategic they gave efficient and effective utilization, which is of control of management
Sam, in that question strategic was wrong and operation was correct
Where as strategic is long term above 3 years I think, that required new resources and the existing would have been used by plannung managers
What about labor strike wuestion?
Yes GVtftf
Strategic was wrong and the other was correct
The words efficient and effective utilization were the ones to pay attention to
That was D and A I think k
Effective and efficient utilizwtion is responsibility of management planning, not strategic planning
YeH, i got a and d as well bro
The reason being coz you were given your fixed costs anyway. U literally had to calculate the highest profit as that was the requirement of the question.
I think people went for utilising more hours rather than more profit
Sam, do you remember your answer for relevant costing?
In operation the statement is resources are use n obtained effeciently and effectively which is wrong it is tactical planning i think soo ??
Most people would have put down wither B D or just D as this used up the more hours but it didn't maximise profit.
I just calculated contribution for each and divided by labor hours
Yes
Ahsan I think the question said about using of specific task resource.
If it just said resource than u would have been correct in saying your point
You had to calculate contribution per limiting factor and then prioritize the products, first D, then A
The answer is only D for maximum profit
Topic lockedNew replies are closed.