Performance Management and Control of the Organisation
This chapter has 1 free video lecture.
5 Types of budget
5.1 Fixed budget
This is a budget prepared at the anticipated level of activity.
If the expected level of activity changes during the period, then the fixed budget becomes unrealistic and will usually be flexed (see below) for use as control.
However, the original fixed budget still very often remains as an overall target – for instance, the profit from the fixed budget will often have been given to head office and used as the target for the period.
5.2 Flexed budget
A flexed budget is when the budget is revised (or flexed) to reflect the actual level of activity.
This budget is useful particularly for control purposes and is what we use in our variance analysis.
5.3 Rolling budget
A rolling budget is one that is kept continually up-to-date by revising at the end of each month and also adding a further month.
For example, on 1 January 2008 prepare a budget for the year to 31 December 2008.
At the end of January 2008, revise the budget for the remaining 11 months of 2008 (in the light of what happened in January), and also prepare a budget for January 2009.
In this way there is always a budget for the coming 12 month period.
The benefits of rolling budgets are that they are likely to be more accurate, and also the work-load of budgeting is spread throughout the year and becomes part of the normal job – again leading to more accurate budgeting.
A company has prepared the following fixed budget for the coming year.
Sales | 10,000 units | |
Production | 10,000 units | |
$ | ||
Direct materials | 50,000 | |
Direct labour | 25,000 | |
Variable overheads | 12,500 | |
Fixed overheads | 10,000 | |
$97,500 | ||
Budgeted selling price $10 per unit. | ||
At the end of the year, the following costs had been incurred for the actual production of 12,000 units.
$ | ||
Direct materials | 60,000 | |
Direct labour | 28,500 | |
Variable overheads | 15,000 | |
Fixed overheads | 11,000 | |
$114,500 |
The actual sales were 12,000 units for $122,000
Prepare a flexed budget for the actual activity for the year
Calculate the variances between actual and flexed budget, and summarise in a form suitable for management.
(Use a marginal costing approach)
Show answerHide answer
6 Methods of budgeting
6.1 Incremental budgeting
This approach is to take the previous year’s results and then to adjust them by an amount to cover inflation and any other known changes.
It is the most common approach, is a reasonably quick approach, and for stable companies it tends to be fairly accurate.
However, one large potential problem is that it can encourage the continuation of previous problems and inefficiencies. All too often the new budget is worked out by taking last year’s figures, then adding an amount for inflation (and often adding another amount for ‘padding’). If we require a wages budget, we will probably ask the wages department to produce it and they (using an incremental approach) will assume that our workers will continue to operate as before. They will therefore simply adjust by any expected wage increases.
As a result, the ‘plan’ for our workers stays the same as before. Nobody has been encouraged to consider critically different ways of operating that may be more efficient. It is at budget time that we perhaps should be considering different ways of operating.
6.2 Zero-based budgeting
With zero-based budgeting we do not consider the previous period. Instead, we consider each activity on its own merits and draw up the costs and benefits of the different ways of performing it (and indeed whether or not the activity should continue).
We then decide on the most effective way of performing each activity.
Clearly any changes to the way an activity is performed may require funding, and there may not be sufficient funding available for all changes proposed, and therefore they are ranked to decide which changes are made.
Although this approach is in principle a much better approach to budgeting, it is time-consuming and also requires much more expertise than incremental budgeting. For this reason, it is often restricted just to a few activities each year in order that training and help may be given to the people involved. Other activities are budgeted using the incremental approach.
6.3 Activity Based budgeting
This is the application of the idea of Activity Based Costing to the process of budgeting, and as such has particular relevance to budgeting for fixed overheads.
At the planning stage, attempts are made to identify which activities drive (cause) various overheads. Costs are spread over these cost drivers using whatever basis appears to be appropriate in the circumstances. A better understanding between costs and their causes should result in better budgets better decision making and better performance.
Budget calculations required for APM
The September 2026 to June 2027 syllabus requires candidates not only to discuss budgeting methods, but also to calculate fixed and flexible, rolling, activity-based, zero-based and incremental budgets. The calculations will normally be straightforward. The important APM skill is to interpret the result and recommend a budgeting method that fits the organisation and its environment.
6.4 Incremental budget calculation
An incremental budget starts with the current cost and adjusts it for expected changes. For example, a department currently costs $240,000. Prices are expected to rise by 4% and activity by 3%.
Incremental budget = $240,000 × 1.04 × 1.03 = $257,088.
This calculation assumes that the existing activities and cost relationships are appropriate. It can therefore preserve waste, budgetary slack and obsolete working practices.
6.5 Rolling budget calculation
Suppose that at 31 March an organisation has budgets for the remaining three quarters of $520,000, $540,000 and $560,000. Management revises these to $525,000, $535,000 and $570,000 and adds a new budget of $590,000 for the following first quarter.
The new rolling twelve-month budget is $525,000 + $535,000 + $570,000 + $590,000 = $2,220,000.
The process is repeated at the end of the next quarter. Rolling budgets are particularly useful where prices, demand or technology change quickly, but continual revision uses management time and can create uncertainty for managers.
6.6 Activity-based budget calculation
An activity-based budget begins with the expected demand for activities and then applies the cost-driver rate.
Activity | Expected activity | Cost-driver rate | Budgeted cost |
|---|---|---|---|
Processing customer orders | 12,000 orders | $18 per order | $216,000 |
Production set-ups | 900 set-ups | $250 per set-up | $225,000 |
Total | $441,000 |
Activity-based budgeting makes the cause of overheads more visible. Management can challenge the number of activities as well as the cost of each activity.
6.7 Zero-based budget calculation
Under zero-based budgeting, activities are organised into decision packages. Each package states the service level, cost and expected benefit. Assume that a public body has $600,000 available:
Decision package | Cost | Assessment |
|---|---|---|
Minimum statutory service | $400,000 | Essential |
Preventative programme | $180,000 | Expected measurable benefit $260,000 |
Public outreach programme | $220,000 | Expected measurable benefit $200,000 |
The statutory service must be funded. Of the remaining packages, the preventative programme ranks higher. The selected budget is therefore $400,000 + $180,000 = $580,000, leaving $20,000 unused or available for a reduced package.
The apparent numerical ranking must not replace judgement. Benefits may be qualitative, long term or difficult to measure.
7 Planning and operational variances
A conventional variance compares actual performance with the original budget or standard. This can give a misleading impression where the original standard has become unrealistic because conditions changed.
Planning variance: the part caused by an inaccurate original standard or by a change in conditions outside the operational manager's control.
Operational variance: the part caused by actual performance compared with the revised, realistic standard. This is normally more relevant when assessing the manager's performance.
The revised standard should be based on information that was not reasonably available when the original standard was set. Managers must not be allowed to revise standards merely to disguise poor performance.
7.1 Material price example
A company originally budgeted a material price of $10 per kg. Before purchasing, an unexpected market shortage increased the general market price to $11.50 per kg. The purchasing manager bought 20,000 kg for $11.20 per kg.
Variance | Calculation | Result |
|---|---|---|
Original material price variance | 20,000 × ($10.00 − $11.20) | $24,000 adverse |
Material price planning variance | 20,000 × ($10.00 − $11.50) | $30,000 adverse |
Material price operational variance | 20,000 × ($11.50 − $11.20) | $6,000 favourable |
The two detailed variances reconcile to the original $24,000 adverse variance. The planning variance indicates that the original standard became unrealistic. The operational variance shows that the purchasing manager performed well by paying $0.30 per kg below the revised market price.
7.2 Using the variances
Investigate why the original standard was wrong and improve the planning process.
Assess operational managers using factors they could reasonably control.
Consider interactions with quality, delivery reliability, inventory and customer service. A favourable price variance may have been achieved by buying inferior material.
Avoid automatically treating every planning variance as uncontrollable. Poor forecasting or failure to update known information may itself indicate weak management.
Use a range of financial and non-financial measures rather than judging performance from a single variance.
Exam focus: At APM level, calculation is only the starting point. Explain what the variance reveals, question the assumptions behind the revised standard and recommend appropriate management action.
Page 2 of 3


