Hello sir, is standard costing the same as flexed budget?
John MoffatJohn MoffatTutor6y ago#1
No! Standard costing is deciding on the budgeted cost per unit. A flexed budget is rewriting the original budget for the actual level of activity (using the standard costs). This is all covered in my free lectures. The lectures are a complete free course for Paper FA and cover everything needed to be able to pass the exam well.
SSafa6y ago#2
Oh ok thank you sir!!
John MoffatJohn MoffatTutor6y ago#3
You are welcome :-)
KKIngsley6y ago#4
Please give me the link to the free lectures. Thanks
John MoffatJohn MoffatTutor6y ago#5
Click on 'ACCA' in the top bar and then click on 'MA'. You will get the main Paper MA page which has links to all of our free resources.