Skip to content

Ask the Tutor ACCA FR

Revenue contracts

FFarida4y ago
Yling Co entered into a contract which is expected to last 24 months on 1 January 20X4. The. The fixed price which has been agreed for the contract is $5 million. At 30 September 20X4 the costs incurred on the contract were $1.6 million and the estimated remaining costs to complete were $2.4 million. On 20 September 20X4 Yling Co received a payment from the customer of $1.74 million which was equal to the total of the amounts invoiced. Yling Co calculates completion of the contract based on the percentage of the project certified as completed. At 30 September 20X4, the percentage certified as completed to date was 38%. Solution; Contract asset: Revenue recognised to date (5m * 38%)= 1,900 Less amounts invoiced (1,740) Answer 160 But in Kaplan way we should do; (5m * 38%)= 1,9000 Estimated cost+cost to date (2,4m + 1,6m)*38%=(1520) Then contract asset =1520+1600-1740=1380 Can someone tell me how to calculate it and which one is correct? Thanks beforehand
P2-D2P2-D2Tutor4y ago#1
Hi, There is no correct way and either way is acceptable. We are waiting to hear from ACCA as to which one they would like to see within the exam itself. Thanks
Sign in to reply to this topic.