June 2025 ACCA Exams

How was your exam? Comments & Instant poll >>

20% off ACCA & CIMA Books

OpenTuition recommends the new interactive BPP books for September 2025 exams.
Get your discount code >>

Planning and Operational variances – Labour

Forums › Ask ACCA Tutor Forums › Ask the Tutor ACCA PM Exams › Planning and Operational variances – Labour

  • This topic has 3 replies, 2 voices, and was last updated 10 years ago by John Moffat.
Viewing 4 posts - 1 through 4 (of 4 total)
  • Author
    Posts
  • October 29, 2014 at 2:02 pm #206575
    Miroslava
    Member
    • Topics: 4
    • Replies: 8
    • ☆

    Hello Mr. Moffat,

    I was hopping you can help me with the answer to a question from BPP Practice and Revision Kit.

    A standard product takes 0.4 h of direct labour time for which the standard wage rate is $14 per hour. During the most recent month, 8000 units of the product were manufactured and these took 3500 hours to make. It is recognised that the work force had been given a large pay rise to $16.50 per hour, which applied throughput the recent month, but which had not been included in the standard hourly rate.
    What is the labour rate planning variance.

    I did my workings as below:
    Original budget: 0.4h x $14
    Revised budget: 0.4h x $16.50 (I assumed that the time spent per unit does not change)

    Revised hours at revised cost (8000u x 0.4=3200h) at $16.50 52800
    Revised hours at std cost 3200 at $14 44800
    Variance $8000 (A).

    In BPP the answer is 8750 (A). Am I wrong in assuming that revised budget is 3200h or BPP uses a different method for calculating the variance?

    Thank you.

    October 29, 2014 at 8:37 pm #206641
    John Moffat
    Keymaster
    • Topics: 57
    • Replies: 54684
    • ☆☆☆☆☆

    There are two different ways of calculating planning and operational variances, which give different answers!
    The examiner has made it clear that both ways will get full marks.

    The way you have done it is actually the more sensible way.
    What BPP have done is use the actual hours of 3500, rather than the revised hours (which is acceptable).

    Because of the problem of there being two acceptable methods, I do not think it can be asked in Section A of the exam (the MCQ’s).

    October 30, 2014 at 6:02 am #206684
    Miroslava
    Member
    • Topics: 4
    • Replies: 8
    • ☆

    Thank you, this made it more clear for me.

    October 30, 2014 at 8:48 am #206714
    John Moffat
    Keymaster
    • Topics: 57
    • Replies: 54684
    • ☆☆☆☆☆

    You are welcome 🙂

  • Author
    Posts
Viewing 4 posts - 1 through 4 (of 4 total)
  • You must be logged in to reply to this topic.
Log In

Primary Sidebar

Donate
If you have benefited from our materials, please donate

ACCA News:

ACCA My Exam Performance for non-variant

Applied Skills exams is available NOW

ACCA Options:  “Read the Mind of the Marker” articles

Subscribe to ACCA’s Student Accountant Direct

ACCA CBE 2025 Exams

How was your exam, and what was the exam result?

BT CBE exam was.. | MA CBE exam was..
FA CBE exam was.. | LW CBE exam was..

Donate

If you have benefited from OpenTuition please donate.

PQ Magazine

Latest Comments

  • EricObi on IAS 37 – Best estimate – ACCA Financial Reporting (FR)
  • Ken Garrett on The nature and structure of organisations – ACCA Paper BT
  • John Moffat on MA Chapter 4 Questions Cost Classification and Behaviour
  • maryrena77 on The nature and structure of organisations – ACCA Paper BT
  • vi234 on MA Chapter 4 Questions Cost Classification and Behaviour

Copyright © 2025 · Support · Contact · Advertising · OpenLicense · About · Sitemap · Comments · Log in