Skip to contentSkip to search

Labour Costs and Remuneration Methods

1 Introduction

This chapter looks at how remuneration is calculated and accounted for.

2 Remuneration methods

Labour costs can arise from:

  • Basic wage or salary

  • Overtime premiums

  • Bonuses

  • Holiday pay

  • Sick Pay

  • Payroll taxes

Many countries pay wages and salaries under a ‘pay as you earn scheme’ which means that the employer deducts the employees’ income tax from the gross wage and pays that over directly to the tax authority. Only the net amount after tax is then paid to the employee.

Employee remuneration can be based on the following approaches:

1. A constant weekly or monthly amount

This is easy to calculate:

Labour cost = remuneration per period x number of periods

2. An amount based on hours worked (basis plus overtime)

52 hours are worked in a week. Basic week is 40 hours, the basic rate of pay = $10, and overtime is paid at time and one half.

$

Basic pay: hours worked @ basic rate 52 x $10

520

Overtime premium : (52 – 40) x $10 x 50%

60

Total pay      

580

3. An amount based on units produced: piecework

Often there is a guaranteed minimum amount of pay so as to comply with minimum wage rate legislation.

Minimum pay/week = $250

Piece rate = $3/unit

If 100 units are made in a week then the pay will be $3 x 100 = $300

If 80 units are made in a week then the pay will be $250 (because the piece rate amount would be only $240).

4. An amount based on productivity

There are many different types of bonus scheme and any question would have to set out the precise rules.

Basic pay = $9/hour for a 40 hour week.

Normal production in that time = 120 units

Bonus = 50% of the time saved on production paid at time and a third

What will be the total wage in a week in which 150 units are made in 40 hours?

Answer

$

Basic pay = 40 x $9

360

150 units should take

50 hours

150 units did take

40 hours

Hours saved

10 hours

Bonus = 50% x 10 x 9 x 1 ⅓

60

Total pay

420

5. An initial amount plus a bonus

Here, for example, the bonus could be part of a profit share. Full instructions would have to be supplied as to how to calculate the amounts.

Employees are paid $6/hour for a standard 40 hour week. Overtime is paid at time and one third.

The employee is expected to make at least 80 units in a week, and to encourage productivity, each unit in excess of 80 will generate an additional payment of $5 less any overtime premium that would relate to the time the additional unit would normally take.

What is an employee’s wages in a week in which 90 units are made and the employee works 44 hours?

Show answerHide answer

Example 1

Note: each unit is expected to take 40/80 = 0.5 hours

Basic wages for 44 hours = 44 x $6 =

US$264

Overtime premium 4 x $6 x ⅓ =

8

Extra units 10 x $5 =

50

Overtime premium that could be associated with the extra units
10 x 0.5 x $6 x ⅓ =

(10)

312

If productive hours are 80% of paid hours, divide productive hours by 0.80 to obtain paid hours. Multiplying by 1.20 is not the same calculation and understates the paid time.

3 The effect of changes in remuneration methods and changes in productivity on unit labour costs

To increase competitiveness, employers will try to reduce unit costs and will often attempt to do this by offering employees productivity payments. Employers need to look at the before and after costs.

Current scheme: $7/hour, 40 hour week.

Overtime = time and a half.

Usually 400 units are produced in 50 hours

Weekly wages = 50 x $7 + 10 x $3.5 = $385

Cost per unit = $385/400 = 0.9625

Proposed scheme: rates as above, but in addition the overtime premium is paid on any hours saved. Assume that 400 units are now made in 44 hours

Possible results:

Hours saved = 50 – 44 = 6

Weekly wages = 44 x $7 +4 x $3.5 + 6 x $3.5 = 343

Cost per unit = 343/400 = 0.8575

4 Gross and net earnings

  • Gross pay: the total amount earned by the employee

  • Net pay: the amount paid to the employee after the employer makes deduction for income tax and certain statutory amounts.

  • Total labour cost to employer: employees’ gross pay plus any additional payroll taxes (and perhaps pension costs) that the employer has to bear.

An employee is paid at the rate of $10/hour.

Tax and other deductions amount to 25% for weekly income in excess of $100

Employer payroll taxes = 10% gross wages

If an employee works 38 hours in a week, what are the employee’s gross pay, net pay and the total amounts that have to be paid by the employer to the tax authorities?

Show answerHide answer

Example 2

Gross wages 38 x $10 =

US$380

Tax and other deductions 25% x (380 – 100) =

(US$70)

Net pay

US$310

Payroll taxes $380 x 10%

US$38

Total payments by employer to tax authorities = $70 + $38 = $108

5 Accounting for labour costs

In addition to being paid whilst working (basic, overtime premiums, productivity bonuses), employees are often also paid when:

  • on holidays

  • ill

  • idle (because, say of machine breakdown)

The labour costs are classified as direct or indirect depending on what caused those costs:

Direct labour costs: all hours worked x normal hourly rate

Indirect labour costs: overtime premium, idle time, sick pay, holiday pay.

In double entry, gross wages are collected in the wages control account first and then split, so that the direct part reaches the units and the indirect part reaches the overhead:

Dr Wages control account with the gross wages and the employer's payroll tax

Cr Cash with the net pay to employees

Cr Payroll tax payable with the employees' deductions and the employer's contributions

…and then, to clear the wages control account:

Dr Work-in-progress with the DIRECT labour cost (hours worked on production at the basic rate)

Dr Production overhead with the INDIRECT labour cost (overtime premium, idle time, sick pay, holiday pay, and the wages of indirect workers)

Cr Wages control account with the total

The production overhead account is then absorbed into cost units in the normal way (chapter 9).

5.1 Idle time

Idle time is time that is paid for but not worked — a machine breakdown, a material shortage, a power cut. The hours are still paid at the basic rate, so they are still a cost; but they cannot be traced to any unit, so they are an indirect cost.

Idle time is usually measured as:

Idle time = hours paid – hours worked

An employee is paid $12/hour for a 38-hour week. In one week a machine breakdown meant that only 34 hours of production work were possible.

$

Direct labour cost: 34 hours worked @ $12

408

Indirect labour cost: 4 hours idle @ $12

48

Gross wages: 38 hours paid @ $12

456

Idle time ratio = 4/38 = 10.5% of hours paid.

Dr Work-in-progress $408; Dr Production overhead $48; Cr Wages control $456.

5.2 Overtime premium

Overtime pay splits into two parts. The BASIC rate for the overtime hours is a direct cost, because those hours were spent making units. The PREMIUM — the extra above the basic rate — is an indirect cost, because it is caused by the factory being busy, not by the unit that happened to be made at 6 p.m.

The one exception: if a customer asks for their job to be rushed and agrees to pay for the overtime, the whole of the overtime, premium included, is a direct cost of that job.

Show the following transactions in wages control account

(a) 31 March, gross wages calculated as $36,000; deductions for employees taxes = $8,000

(b) 31 March, employer’s payroll tax calculated as $4,000

(c) 1 April, employees paid amounts due

(d) 15 April, tax authorities paid amounts due

Show answerHide answer

Example 3

Wages control account

31/3 Work in progress account

36,000

31/3 Work-in-progress account

4,000

1/4 Cash (paid to employees)

28,000

15/4 Cash (paid to tax authorities)

12,000

40,000

40,000

Practice question

Which of the following is the correct treatment?

Practice question

Under most systems of tax, what do employers pay to employees?

When overtime is caused by a general disruption, charge the basic pay for traceable work directly but treat the premium as indirect. The whole overtime amount is direct only when the specific customer or job caused the overtime.

Practice questions

Accounting for Labour

10 questions

Answer the questions one at a time. Your progress is saved so you can leave and come back.

Open chapter practice