Discounted Investment Appraisal Techniques (Net Present Value and IRR)
1 Introduction
Chapter 10 covered two appraisal methods that ignore the time value of money. This chapter covers the two that do not: net present value (NPV) and the internal rate of return (IRR). NPV is the technically correct method and the one the rest of this section of the syllabus is built on.
The chapter also covers two shortcuts that appear constantly in exam questions — annuities and perpetuities — which are simply faster ways of discounting a cash flow that repeats unchanged.
2 Discounted cash flow — net present value
This recording works Examples 1, 2 and 3 and covers the whole of sections 2 and 3. It is sound throughout; the notices are about what it points you at, not about what it teaches.
One. The tutor says the present value and annuity tables are "at the beginning of the notes … on page three". They are in the front matter of the printed 2023 PDF and are not in this digital chapter set. Use the formulae in sections 2.2, 4.1 and 4.2, which give the same numbers, and use the tables supplied in the examination itself.
Two. He describes the tables as running "up to 20%, for any number of years, up to 15%". He means up to 15 years; the 15% is a slip.
Three. The recording is in pounds throughout — "£80,000", "£11,500". The notes are in dollars and the figures are otherwise identical.
Four. Example 4 is not on the tape, although the closing minutes of this recording — on how far the cost of capital could be wrong before the decision changes — are the substance of its answer.
The discounted cash flow approach takes the net cash flows arising from an investment decision and adjusts them for the time value of money.
2.1 The time value of money
Time value of money
$1 received or paid today is worth more than $1 received or paid at some future date, and the difference grows the further into the future the flow lies.
The reason is the cost of money itself. If the business has borrowed to fund the project it pays interest; if it used its own cash it has given up the interest that cash could have earned. Either way, money tied up in a project has a cost, and that cost is what discounting measures.
The time value of money is brought into an appraisal by discounting future cash flows at the company's required rate of return — variously called the cost of capital, the required rate, or the weighted average cost of capital. Each future cash flow is converted into its present value: the amount it is worth today.
2.2 Discount factors
The present value of a single cash flow is found by multiplying it by a discount factor:
Discount factor = 1 ÷ (1 + r)n
where r is the cost of capital as a decimal and n is the number of years away that the cash flow arises.
Present value tables give these factors, rounded to three decimal places, for rates up to 20% and for up to 15 years. They are provided in the P2 objective test examination. Where the rate you are given is not in the tables — 4.5%, say — use the formula above.
The sum of the discounted cash flows is netted against the initial cost of the project. If the result is positive the project is financially acceptable; if it is negative the project should be rejected.
The net present value is expressed as an absolute amount of money, not as a percentage or a ratio. That is one of its strengths — it states how much better off the shareholders are — and it is why NPV cannot be used on its own to rank projects of very different sizes when capital is rationed (chapter 13).
2.3 Interpreting the net present value
Result | What it means | Decision |
NPV > 0 (positive) | The project earns more than the required rate of return. | Financially viable — accept. |
NPV = 0 | The project earns exactly the required rate of return; it breaks even in present value terms. | Marginal — normally accepted, since the required return has been met in full. |
NPV < 0 (negative) | The project earns less than the required rate of return. | Not financially viable — reject. |
The decision rule is NPV greater than zero, not greater than one. A rule written as "NPV > 1 (positive value)" would reject a project with an NPV of $0.50 — a positive value — under a rule that calls itself positive. There is no threshold: any NPV above zero means the project earns more than the cost of capital.
Net present value
A machine will cost $80,000. It has an expected life of 4 years with an anticipated scrap value of $10,000.
Expected net operating cash inflows for each year are as follows:
Year | $ |
1 | 20,000 |
2 | 30,000 |
3 | 40,000 |
4 | 10,000 |
The cost of capital is 10% p.a.
Required
Calculate the net present value of the investment and determine whether the project should be accepted.
Show answerHide answer
Beyond the net present value
Consider the project appraised in Example 1.
Required
Suggest other factors that should be considered before the investment is accepted.
State the advantages of the net present value method.
State the disadvantages of the net present value method.
Show answerHide answer
3 The internal rate of return (IRR)
The practical difficulty with discounted cash flow is that it is very hard to establish a company's true cost of capital. In Example 1 the project was accepted on the basis that the cost of capital is 10%. Suppose it is not 10% but 15%: a higher rate discounts the cash flows more heavily, so the NPV will be lower, and it may become negative.
Because the cost of capital is uncertain, it is useful to know the break-even rate of return for the project — the discount rate at which its NPV is exactly zero. That rate is the internal rate of return.
Internal rate of return
The discount rate at which the net present value of a project is zero.
The IRR is found by interpolation: the cash flows are discounted at two different rates, one giving a positive NPV and one a negative NPV, and the answer is apportioned between them.
IRR ≈ L + [NPVL ÷ (NPVL − NPVH)] × (H − L)
where L is the lower discount rate, H the higher discount rate, NPVL the NPV at the lower rate and NPVH the NPV at the higher rate.
The result is only an approximation, because the relationship between the discount rate and the NPV is a curve rather than a straight line and interpolation treats it as straight. That is why the symbol is ≈, "approximately equal to". The approximation is good enough: the answer is used to judge how much room there is for error in the cost of capital, not as a precise figure.
Which two rates you choose does not matter much. If the question tells you which to use, use them. If not, any two sensible guesses give an answer within a fraction of a percent of each other — the technique is robust, and it is far quicker than plotting the curve.
Internal rate of return
Using the project cash flows and the result obtained in Example 1:
Required
Calculate the net present value of the project at a discount rate of 15%.
Estimate the internal rate of return of the project, using your result from Example 1 and your answer to part (a).
Explain the significance of the internal rate of return you have calculated.
Show answerHide answer
Advantages and disadvantages of IRR
Required
State the advantages of using the internal rate of return.
State the disadvantages of using the internal rate of return.
Show answerHide answer
4 Annuities and perpetuities
This recording works Examples 5 to 8 and is correct throughout. Three notices.
One. It is in pounds; the notes are in dollars.
Two. The tutor misreads Example 5's opening line as "a machine will cost £45,000 a year" and corrects himself immediately — the cost is a one-off $45,000.
Three. As in the previous recording, the annuity tables he refers to are in the printed front matter and not in this digital set. Section 4.1 gives the formula.
The perpetuity section is illustrated with a divorce-settlement analogy. The arithmetic it carries — $12,000 a year forever is worth $120,000 today at 10%, because $120,000 in the bank generates $12,000 a year — is the clearest explanation of 1 ÷ r anywhere in the paper.
4.1 Annuities
Most appraisal questions produce a different cash flow in each year, so each year has to be discounted separately. Occasionally, though, a payment or receipt is the same amount each year for a fixed number of years — a fixed annual rent, for instance. A constant annual cash flow for a fixed number of years is an annuity.
Because the amount is the same each year, it can be multiplied by the total of the individual discount factors rather than by each of them in turn. That total is the annuity factor, and it is given by:
Annuity factor = (1 − (1 + r)−n) ÷ r
where r is the discount rate as a decimal and n the number of years. Cumulative present value tables give these factors and are provided in the P2 objective test examination; be able to use both the tables and the formula.
The annuity factor assumes the first cash flow arrives at the end of year 1. Where the flow starts later, the factor has to be adjusted — see Example 6. Reading "years 4 to 13" as a ten-year annuity factor, or as a 14-year one, are the two errors this topic generates.
Annuity
A machine will cost $45,000 and is expected to generate $8,000 p.a. for the following 8 years.
The cost of capital is 15% p.a.
Required
Calculate the net present value of the investment.
Show answerHide answer
Deferred annuity
The cost of capital is 12% p.a.
Required
What is the present value of $20,000 that is first receivable in 4 years' time and thereafter each year for a total of 10 receipts?
Show answerHide answer
4.2 Perpetuities
Where an identical cash flow is expected to continue indefinitely it is a perpetuity. Nothing genuinely lasts forever, but a flow expected to continue for so long that its end cannot sensibly be forecast is treated as one.
The present value factor for a perpetuity is:
Perpetuity factor = 1 ÷ r
where r is the discount rate as a decimal. The logic is worth holding on to: at 10%, $120,000 placed on deposit generates $12,000 a year forever, so the right to $12,000 a year forever is worth $120,000 today. That is 12,000 ÷ 0.10.
Perpetuity factors are not provided in the objective test examination, so 1 ÷ r must be remembered. And, exactly as with annuities, 1 ÷ r assumes the first flow arrives at the end of year 1 — a deferred perpetuity needs the same subtraction (Example 8).
Perpetuity
A machine costs $100,000 and is expected to generate $12,000 p.a. in perpetuity.
The cost of capital is 10% p.a.
Required
What is the net present value of the project?
Show answerHide answer
Deferred perpetuity
The rate of interest is 5% p.a.
Required
What is the present value of $18,000 first receivable in 5 years' time and thereafter annually in perpetuity?
Show answerHide answer
5 Choosing between NPV and IRR
Both methods use cash flows and both recognise the time value of money, so on an ordinary accept-or-reject decision they agree: a project with a positive NPV at the cost of capital has an IRR above the cost of capital, and vice versa.
They can disagree when ranking mutually exclusive projects, because IRR is a percentage and takes no account of scale. Where they conflict, NPV is correct, because NPV measures the absolute increase in shareholder wealth and that is the objective. IRR's proper role is to say how much room there is for the cost of capital to be wrong.
Discount each future cash flow by 1 ÷ (1+r)n and add them up. NPV > 0, accept — not NPV > 1. IRR is the rate at which NPV is zero, found by interpolating between one positive and one negative NPV, and it measures the margin of error in the cost of capital. An annuity factor is (1 − (1+r)−n) ÷ r; a perpetuity factor is 1 ÷ r; both assume the first flow is at the end of year 1, so subtract for a deferred start.
6 Test your knowledge
Two quick checks before you move on: work through the flashcards to fix this chapter’s key terms and definitions, then sit the objective questions for exam-style practice. Both mark themselves and explain the answers as you go.