variance

BBroamawesome10y ago
Will sales qty variance for 2 prodcts sold in a a sales mix differ according to the method used? For eg refer qs 73 of bpp revsn kit(carad).in that i used the method given in bpp text bk to get sales qty variance of 40700 in total (plasma-29600 &lcd-11100) ,but the answer looked different
BBroamawesome10y ago#1
Different in the sense, the individual variances and not the total
John MoffatJohn MoffatTutor10y ago#2
No - there is only one answer (even though you can use different methods by all means, they all will give the same answer).
BBroamawesome10y ago#3
Then please explain to me what went wrong my calculations were:- Plasma. LCD Bdgtd qty. 590. 590 Act qty. 750. 650 Difference. 160. 60 Wghtd std cont pu. 185. 185 Variance. 29600. 11100
John MoffatJohn MoffatTutor10y ago#4
If you want to calculate the sales quantity variance using the weighted standard contribution, then you apply it to the difference between the total actual and budgeted sales (not the sales for each unit separately). This is because the sales quantity variance assumes they sell in standard mix. (The mix variance deals with any change of mix).