- September 5, 2019 at 1:36 pm #545093
In the process of service cost analysis it is important that plant cost should be compared with the actual cost, and difference must be investigated.
Q. T/ F
Ans T
But what I think should be false since each service is different from another and it cannot be compared due to the feature of heterogeneity.Thank you
September 5, 2019 at 4:51 pm #545148Are you sure that the question says ‘plant’ cost because if it does then the question does not really make sense (unless there is more wording in the question that you have not typed).
September 6, 2019 at 4:33 am #545210It is planned cost , wrongly typed
September 6, 2019 at 8:50 am #545229In that case the question does make sense. Whatever the type of costing is, it is important to compare the actual cost with the planned (budget) cost and if it is different then investigate why it is different.
September 6, 2019 at 12:50 pm #545257Thank you sir , I gave my exam today and passed with 85% in first attempt just becoz of only and only opentution.
Your doubt solving approach is really kind .September 6, 2019 at 3:57 pm #545309Many congratulations on passing – I am very pleased for you 🙂