Performance Prism

ZZulfiqar10y ago
1- If question ask to apply performance prism ( does not mention about performance measures) do we have to mention performance measures for each facet. 2- having difficulty in producing measures for Strategy and process. (How they will be different) Example would help Thanks
kengarrettkengarrettTutor10y ago#1
Generally the performance prism will be asked in the context of a question where you have to apply it so I think that a couple of performance measures for each face would produce a more useful answer. Strategy: could be cost leadership. Process: could be high reliance on advanced automation and JIT Resources: sophisticated IT to allow accurate forecasting of demand, scheduling of machinery use and ordering of parts.
ZZulfiqar10y ago#2
Thanks . for second part Measures could be Strategy-Cost per unit Process- No of errors after IT implementation vs Before implementation Right ? /guide me
kengarrettkengarrettTutor10y ago#3
That would be fine.