A1Alex 19886y ago
Hi, could you please help in understanding of 1st task in PM Notes. I do not understand why Machining distribution in answers calculated as: A B C 23 404 29256 2340 when in conditioning of Machines hours per unit we have: A B C 2 2 2 When the total machines costs 55 000 More reasonable calculations are the follow: A B C 18 333 18 333 18 333 Is it a mistake in answers or my logic is incorrect? Thanks a lot.
John MoffatJohn MoffatTutor6y ago#1
Your logic is not correct and there is no mistake in the notes. Watch the free lecture on this because I work through the example and explain. It is pointless to use the notes without watching the free lectures that go with them. They are not a Study Text - they are lecture notes and it is in the lectures that I explain and expand on the notes. If you are not watching the lectures for any reason then you need to buy a Study Text from one of the ACCA approved publishers and study from there. However you choose to study it is vital that you buy a Revision Kit, because that is full of past exam and other exam-standard questions for practice, and practice is essential to passing the exam.
A1Alex 19886y ago#2
Ok, thanks, I`m watching it today.
John MoffatJohn MoffatTutor6y ago#3
You are welcome :-)