Hi sir, in June 2012 quest 1 - I was wondering how come in the answer didn't the examiner re calculate the semi variable machine cost? In fact he just included the fixed cost Thanks
John MoffatJohn MoffatTutor10y ago#1
No he didn't. Note 4 of the question says that the semi-variable cost of machine set-up costs includes fixed costs. The remainder is variable and has been included in the totals of the variable costs.
SSteven10y ago#2
Hi Sir, Yes ok got it now thanks!
John MoffatJohn MoffatTutor10y ago#3
Great :-)