A company makes a product for which the standard labour time is 2 hours per unit. The budgeted production hours in a week were 820. During the week the production staff were able to produce 380 units. The employees worked and paid for 800 hours. During the week 20 production hours were lost due to shortage of material. calculate efficiency,capacity,activity ratios
Presumably you have the answer in the same book that you found the question, so do say which bit of the answer you do not understand and I will try to help.
(I assume that you have watched our free lecture on this?)