Skip to content

Ask the Tutor ACCA MA

Labour efficiency variance mock exam question

AAnkit8y ago
Hi, I do not understand the solution at all sir. To calculate efficiency variance, I know that it is Actual hours * standard rate and you compare the answer to Standard hours * Standard Rate. I think I do not know how to work out standard rate for labour. Please could you explain. The question is: Company has budgeted labour cost of $180,000 for the production of 30,000 units per month. Each unit is budgeted to take 3 hours of labour. Actual cost is $160,000 for 28,000 and 85,000 hours were worked. What is the labour efficiency variance? Could you please explain how to get the standard rate because I still do not understand from the solution provided? Many thanks
John MoffatJohn MoffatTutor8y ago#1
They budgeted on working 30,000 units x 3 hours per unit = 90,000 hours. The budgeted labour cost is $180,000. Therefore the standard rate per hour = $180,000 / 90,000 = $2 per hour.
Sign in to reply to this topic.