KKanan6y ago
Hi Dear Tutor, I have a question. B) why i take project E 1st which its PI is only 1 but others more than 1 and in the answer the first project is taken E why? Thanks in advance
John MoffatJohn MoffatTutor6y ago#1
Because the question says that it must be undertaken regardless of its financial acceptability!
KKanan6y ago#2
Understood
John MoffatJohn MoffatTutor6y ago#3
You are welcome :-)