A job cost estimates include 630 productive labour hours. In, addition, it is anticipated that idle time will be 10% of the total hours paid for the job. The wage rate is $12 per hour.
What is the total estimated labour cost?
(a) $6,804
(b) $7,560
(c) $8,316
(d) $8,400
Correct answer is $8,400
But my answer is option a and option c
FIA Forums
Labour cost
If 630 productive hours are needed, this is after the idle hours.
If 10% of hours paid for are idle, 630 represents the remaining 90% productive hours. 100% of the hours is therefore 630/0.9 = 700. [Check: 90% of 700 = 630].
Labour cost is therefore 700 x $12 = $8,400
I did it the other way around.
630 x 10/90 = 70
630 + 70 = 700
700 x $12 = $8400
No problem. Whichever way you see it!
Sign in to reply to this topic.
