((deleted)6y ago
I have understood that To be cost effective we need benefits more than cost of implementing ABC. This means that fixed cost will be low and variable production cost will be higher to be cost effective ????
John MoffatJohn MoffatTutor6y ago#1
No. It means that the savings are more than the costs and therefore there is a net saving.
((deleted)6y ago#2
Thank you sir God bless u always
John MoffatJohn MoffatTutor6y ago#3
You are welcome :-)