Direct labour efficiencyForums › ACCA Forums › ACCA MA Management Accounting Forums › Direct labour efficiencyThis topic has 2 replies, 3 voices, and was last updated 8 years ago by John Moffat.Viewing 3 posts - 1 through 3 (of 3 total)AuthorPosts February 25, 2017 at 8:49 am #374101 geokchengMemberTopics: 17Replies: 12☆Hi Sir,Refer to Acca specimen exam section b qn no 2a. The answer for this qn is C.But based on my understanding the answer should be D.Actual hour worked is 150,000 hours – standard hour for actual production (26,000 units x 6hours) x standard cost per hour ($8) February 28, 2017 at 6:30 pm #374804 secondstarMemberTopics: 16Replies: 220☆☆☆If you can write down the question here, it would be much better. I would answer you but i can’t find the question you’re referring to. March 1, 2017 at 7:03 am #374836 John MoffatKeymasterTopics: 57Replies: 54636☆☆☆☆☆If you want for me to answer then you must ask in the Ask the Tutor Forum – this forum is for students to help each other.AuthorPostsViewing 3 posts - 1 through 3 (of 3 total)You must be logged in to reply to this topic.Log In Username: Password: Keep me signed in Log In