Ref to question 33. How did they get $0.50 per unit. I see they have 9000/6. how do we get the 6?
Ask the Tutor ACCA PM
ABC Costing pg 10 in the Revision Kit BPP- Linacre CO
The labour is 10 minutes per unit.
There are 60 minutes in an hour, and so each unit takes 10/60 or 1/6 of an hour.