Skip to contentSkip to search

Interest Rate Risk Management

CIMA Free Mock Exam

1 Introduction

Interest rate risk arises when an entity does not know how much interest it will have to pay on its borrowings, or how much it will earn on its deposits — whether those borrowings and deposits already exist or are only planned.

The consequences run further than the interest line itself. An entity that cannot forecast its interest cost cannot complete a reliable cash flow forecast; changes in interest rates alter the weighted average cost of capital and therefore the outcome of a net present value appraisal; and an entity that committed itself to floating rate borrowing when rates were low may find a rise in rates more than it can carry.

Benchmark reference rate

A floating rate of interest is quoted as a margin over a benchmark reference rate — a published rate, specific to a currency, that moves with the money market. In US dollars the benchmark is SOFR, the Secured Overnight Financing Rate; other currencies have their own. Older material refers to LIBOR, which ceased in 2023; the mechanics are unchanged, only the published rate has a different name.

In this chapter a floating rate is written as BR + a margin, where BR is the benchmark reference rate for the currency concerned. The rate itself is never examinable; the margin, and what the margin depends on, is. The same convention is used in chapter 5.

What interest rate management is for

The aim is not to guarantee the entity the lowest interest rate it could ever have paid. It is to limit the uncertainty, so that the entity can plan. Exactly the same point governs currency risk management in chapter 9, and it is the point most often missed in an answer that recommends whichever instrument turned out best with hindsight.

2 Where interest rate risk comes from

The position

What is uncertain

What the entity fears

Floating rate borrowing already drawn

Every future interest payment

A rise in rates

Floating rate deposit already placed

Every future receipt

A fall in rates

Fixed rate borrowing already drawn

Nothing in cash terms — but the rate is locked and the market value of the debt moves

A fall in rates, which leaves the entity paying above the market

A borrowing planned for a future date

The rate that will be available on the day it is drawn

A rise in rates before drawdown

A deposit planned for a future date

The rate available on the day it is placed

A fall in rates before then

Borrowing that has to be refinanced on maturity

Both the rate and whether the money is available at all

A rise in rates, or a closed market, on the refinancing date

The fourth and fifth of those are the ones examiners return to, because the exposure exists before any interest is payable at all. Chapter 8 works the illustration: a company that has decided on 1 June to borrow for six months from 1 September is exposed to rate movements over the three months in between, even though the loan itself will be at a fixed rate once drawn.

Every instrument in sections 4 to 8 is an answer to one or more of the rows above. Section 9 sets out how to choose between them.

3 Basic and internal approaches

Before any derivative is bought, three things can be done with the entity's own borrowings and deposits.

3.1 Smoothing

Borrowings, or deposits, are simply divided between fixed rate and floating rate. If rates then rise, only the floating part costs more, and the effect is smaller than it would have been had everything been floating. Deposits can be smoothed in the same way.

There is no science in it. The entity looks at what it can afford, forms a view of where rates are going, and splits the book accordingly. It is not a hedge; it is a way of not being wholly wrong.

3.2 Matching

Matching requires the entity to have both borrowed and deposited money, and works best when the two amounts are close. Because both move with the same benchmark, the movements largely cancel.

Suppose the deposit rate is BR + 1% and the borrowing rate BR + 4%, that $500,000 is on deposit and $520,000 borrowed, and that BR is currently 3%.

BR at 3%

BR at 5%

Interest paid: $520,000 at BR + 4%

$36,400

$46,800

Interest received: $500,000 at BR + 1%

($20,000)

($30,000)

Net cost

$16,400

$16,800

A two-point rise in the benchmark has changed the net cost by only $400 — and that $400 is entirely explained by the $20,000 by which the borrowing exceeds the deposit: $20,000 × 2% = $400. What is hedged is the matched $500,000; what is exposed is the mismatch.

3.3 Asset and liability management

Matching deals with amounts. Asset and liability management deals with periods — how long the borrowings last against how long the assets they fund produce income. The problem is not confined to floating rate arrangements: fixed rate money can mature at the wrong time just as easily.

Suppose an entity borrows on a ten-year mortgage secured on a new property at a fixed rate of 6% a year, and lets the property for five years at a rent yielding 8% a year. All is well for five years. Then a new lease has to be negotiated, and if rental yields have fallen to 5% the entity begins to lose money on a loan it cannot repay for another five years.

The answer was to match the period of the borrowing to the period of the lease, so that the two decisions come up for renewal together and the entity can take advantage of lower rates if they occur. The same idea appears in chapter 5 as the maturity dimension of the target debt profile, and the risk it manages is refinancing risk.

4 Forward rate agreements

A forward rate agreement (FRA) fixes the rate of interest on a borrowing or deposit that will be taken out at a future date, for a set period. The entity still borrows from whichever bank it chooses, at whatever rate is then available; the FRA provider — which may be a completely different institution — pays or receives the difference between the rate that turns out and the rate agreed, so that the two together give the entity the fixed rate it wanted.

Naming and direction

An FRA is named by the two dates, both measured from today. One that starts in three months and ends nine months after that is a 3 – 12 FRA, because it ends twelve months from now.

If you are borrowing, you buy an FRA. If you are depositing, you sell one.

FRAs are over-the-counter instruments: they are negotiated individually with a bank, for any amount and any period.

A forward rate agreement

Nero's cash flow forecast shows that it will have to borrow $2 million in four months' time, for a period of three months. The company fears that by the time the loan is taken out interest rates will have risen.

The current interest rate is 5%, and 5% is the rate offered on the FRA that Nero needs.

Required

  1. State what FRA is needed.

  2. Show the cash flows if the interest rate has risen to 6.5% when the loan is taken out.

  3. Show the cash flows if the interest rate has fallen to 4% when the loan is taken out.

Show answerHide answer

A forward rate agreement

(a) The FRA needed

Nero is borrowing, so it buys an FRA. The borrowing starts in four months and ends three months after that — seven months from today — so it is a 4 – 7 FRA at 5% on a principal of $2 million.

(b) If the rate has risen to 6.5%

Interest paid at the market rate: $2m × 6.5% × 3/12

$32,500

Less: receipt under the FRA: (6.5% − 5%) × $2m × 3/12

($7,500)

Net payment

$25,000

(c) If the rate has fallen to 4%

Interest paid at the market rate: $2m × 4% × 3/12

$20,000

Add: payment made under the FRA: (5% − 4%) × $2m × 3/12

$5,000

Net payment

$25,000

In both cases the net cost is $25,000, which is 5% on $2 million for three months. That is the whole point: the FRA has fixed the rate at 5% whichever way the market moved.

Note the direction of the second line in part (c). When rates fall the entity pays the FRA provider — it is not a receipt. An FRA is binding in both directions, and giving up the benefit of a fall is the price of being protected against a rise.

5 Interest rate futures

An interest rate future is a standardised, exchange-traded contract. Buying one creates the right to receive interest at a given rate; selling one creates the obligation to pay interest at a given rate.

5.1 Price, and why it moves the way it does

The price of an interest rate future

Futures price = 100 − the interest rate

So a future priced at 92.00 corresponds to an interest rate of 8%. A rise in interest rates reduces futures prices; a fall in interest rates increases them.

The reason is worth working through rather than memorising. Suppose a contract lets its holder receive interest at 5%, which is the current market rate. If market rates rise to 6%, a depositor can get 6% in the market and only 5% under the contract, so nobody will pay as much for it and the price falls. From the other side, a borrower who has to pay 6% in the market would rather pay 5% under the contract, so there are many willing sellers, and that too pushes the price down until buyers and sellers balance.

5.2 How futures are traded

  • Contracts are for a standard amount and a standard period of three months. The examples in this chapter use a contract of $500,000; the actual size differs between currencies and exchanges.

  • Only whole contracts can be dealt, so the number needed is:

Number of contracts = (Amount to be hedged ÷ Contract size) × (Period of the loan or deposit ÷ 3 months)

So covering a $3 million loan for six months needs $3m ÷ $0.5m × 6 ÷ 3 = 12 contracts. The second fraction is there because each contract only covers three months.

  • A tick is the smallest movement in the price, 0.01 of a percentage point, and its value is the contract size × 0.01% × 3/12.

  • An initial margin is paid when the position is opened, and further margin is called if it moves against the holder. The margin is not the cost of the hedge; it is a deposit against the position.

  • Contracts trade on futures exchanges rather than being arranged individually with a bank.

5.3 Which way to deal

A futures hedge is two parallel transactions: the entity borrows or deposits in the market at whatever rate then applies, and takes a futures position designed so that the profit or loss on it offsets the movement in the interest.

The entity fears

If that happens, futures prices

So it

and closes by

Depositing and earning interest

a fall in rates

rise

buys futures now

selling them later at a higher price

Borrowing and paying interest

a rise in rates

fall

sells futures now

buying them back later at a lower price

The summary rule

Depositing: buy futures, then sell. Borrowing: sell futures, then buy.

If rates move the other way, the position still works — in reverse. A borrower who sold futures and then saw rates fall pays less interest but makes a loss on the futures; a depositor who bought futures and then saw rates rise earns more interest but loses on the futures. In both cases the combined outcome is stable, which is the object of the exercise.

Students often ask how something can be sold before it has been bought. Nothing is being delivered when a future is sold: it is a contract to be settled in the future, and it is completed by buying an equal and opposite contract before the settlement date.

Hedging with interest rate futures

Today is 3 October and interest rates are 8% a year. X will need to borrow $6 million for six months, starting on 1 January. Three-month January interest rate futures are available at 92.00, and the contract size is $500,000.

Assume that on 1 January interest rates have risen to 10% and the futures price has fallen to 90.00.

Required

Show how interest rate futures could be used to hedge the risk, and calculate the outcome on 1 January.

Show answerHide answer

Hedging with interest rate futures

Setting up the hedge

X is borrowing and fears a rise in rates, so it sells futures now and buys them back on 1 January.

($6m ÷ $500,000) × (6 months ÷ 3 months) = 24 contracts

The futures position

Sell 24 January contracts on 3 October at

92.00

Buy them back on 1 January at

90.00

Gain

2.00

A gain of 2.00 is 2% a year on each contract, and each contract runs for three months:

24 × $500,000 × 2% × (3 ÷ 12) = $60,000

The overall position

Interest on the borrowing: $6m × 10% × 6/12

$300,000

Less: gain on the futures

($60,000)

Net cost

$240,000

$240,000 is 8% a year on $6 million for six months — the rate that applied on 3 October, which is exactly what the hedge set out to lock in.

5.4 Why a futures hedge is never perfect

  • Basis risk. Futures prices do not move exactly in line with interest rates, so the gain on the futures does not precisely offset the movement in the interest.

  • Contract size and dates. Only whole contracts of a standard size and a standard maturity can be dealt, so the hedge rarely fits the exposure exactly.

  • Margin. The position has to be funded, and further margin may be called before the hedge matures.

An answer recommending a futures hedge should say all three.

6 Interest rate options

Interest rate options — also called interest rate guarantees — protect the entity against an adverse movement while leaving it free to benefit from a favourable one. They work like an insurance policy:

  1. a premium is paid to take out the protection, and it is not returnable whether the protection is used or not;

  2. if rates move unfavourably the entity exercises the option;

  3. if rates move favourably the entity lets the option lapse and simply takes the better market rate.

The options are written on interest rate futures, so they give the right, but not the obligation, to buy or to sell a future at an agreed price on an agreed date. Contract sizes and periods are those of the underlying future (section 5.2), so the number of contracts is calculated in exactly the same way.

6.1 Using options when borrowing

With plain futures a borrower would sell now and buy later. With options it buys the right to sell a future at an agreed price — a put option. Suppose that price is 95.

If interest rates

the futures price

and the borrower

with the result that

rise

falls, say to 93

exercises: buys at 93, sells at 95 under the option

the gain offsets the extra interest paid

fall

rises, say to 97

lets the option lapse

it keeps the benefit of the lower interest rate, less the premium

6.2 Using options when depositing

With plain futures a depositor would buy now and sell later. With options it buys the right to buy a future at an agreed price — a call option, again say at 95.

If interest rates

the futures price

and the depositor

with the result that

fall

rises, say to 97

exercises: buys at 95 under the option, sells at 97

the gain offsets the lower interest earned

rise

falls, say to 93

lets the option lapse

it keeps the benefit of the higher interest rate, less the premium

The two rules together

Borrowing: buy a put. Depositing: buy a call.

Options give borrowers a maximum cost and depositors a minimum income, while leaving the door open to a better outcome. That asymmetry is what the up-front, non-returnable premium pays for.

7 Caps, floors and collars

The three named techniques for shaping the risk profile are built out of the options in section 6.

What it does

How it is built

Cap

Sets a maximum interest rate for a borrower. If the actual rate is lower, the option lapses.

The borrower buys a put option on interest rate futures.

Floor

Sets a minimum interest rate for a depositor. If the actual rate is higher, the option lapses.

The depositor buys a call option.

Collar

Confines the interest paid, or earned, within a band, in return for a much smaller net premium.

A borrower buys a cap and sells a floor; a depositor buys a floor and sells a cap.

A collar is the first case in this chapter of selling an option rather than buying one, and it is worth being clear about what that costs. Selling a floor means someone else has the right to be paid if rates fall below the floor rate; if they do, the entity has to pay. So it has given up the benefit of a large fall in rates, and the premium it received for doing so is what makes the cap affordable.

A collar

An entity will borrow $10 million for three months, starting in two months' time. It buys a cap at 6.5% for a premium of $7,500 and sells a floor at 4.5%, receiving a premium of $5,000. The net premium is therefore $2,500.

Rate on the day the loan is drawn

7%

5%

4%

Interest on $10m for three months

$175,000

$125,000

$100,000

Received under the cap: (7% − 6.5%) × $10m × 3/12

($12,500)

—

—

Paid under the floor sold: (4.5% − 4%) × $10m × 3/12

—

—

$12,500

Net premium

$2,500

$2,500

$2,500

Total cost

$165,000

$127,500

$115,000

Equivalent annual rate

6.6%

5.1%

4.6%

The collar has confined the cost to a band between 4.6% and 6.6%. Inside the band the entity pays the market rate plus the net premium; outside it, one or other option bites. Had it bought the cap alone it would have kept the whole benefit of the fall to 4% — and paid $7,500 rather than $2,500 for the protection.

8 Interest rate swaps

In an interest rate swap two parties agree to exchange interest payments with each other over an agreed period — typically one paying a fixed rate and the other a floating rate on the same notional amount. Neither party's own borrowing changes; what changes is who ends up bearing which kind of interest.

8.1 Why there is anything to gain

A swap only works if there is an advantage to both parties, and the advantage arises because lenders price the two parties differently in the fixed market and in the floating market. The difference between those two differences — the quality spread differential — is the total gain available, and it is what the parties divide between them.

8.2 A swap between two companies

Company A can borrow at a fixed rate of 8%, or at a floating rate of BR + 2%. Company B can borrow at a fixed rate of 9%, or at a floating rate of BR + 5%. A wants fixed and B wants floating.

Fixed

Floating

Company A

8%

BR + 2%

Company B

9%

BR + 5%

Difference (B − A)

1%

3%

The spreads differ by 2%, and that 2% is the gain available. Confirm it by totalling the two ways the money can be raised:

If each borrows what it wants: A fixed 8% + B floating BR + 5%

BR + 13%

If each borrows what it does not want: A floating BR + 2% + B fixed 9%

BR + 11%

Total saving available

2%

So each borrows the kind it does not want and they swap. Splitting the 2% equally, A should end at 8% − 1% = 7% fixed and B at BR + 5% − 1% = BR + 4%. The legs that achieve it are: A pays B 5% fixed, and B pays A BR.

Company A

Company B

Pays its own lender

BR + 2%

9%

Pays the other party

5%

BR

Receives from the other party

(BR)

(5%)

Net cost

7% fixed

BR + 4%

Cost of borrowing that way directly

8%

BR + 5%

Saving

1%

1%

The parties can divide the 2% however they negotiate; an equal split is the usual assumption where a question does not say otherwise. What matters is that each ends up better than it could have done alone — otherwise it would not sign.

8.3 A swap arranged through a bank

Two companies finding each other, trusting each other and having exactly complementary needs is difficult in practice. Swaps are therefore usually arranged with a bank, which takes the other side of both legs and keeps part of the saving.

Company A can borrow at a fixed rate of 10% or at BR + 1%, and prefers fixed. Company B can borrow at 9% fixed or at BR + 0.5%, and prefers floating. Note that B can borrow more cheaply than A in both markets; that does not prevent a swap, because what matters is the comparative difference — 1% in the fixed market against 0.5% in the floating market, so 0.5% is available.

If each borrows what it wants: A fixed 10% + B floating BR + 0.5%

BR + 10.5%

If each borrows what it does not want: A floating BR + 1% + B fixed 9%

BR + 10.0%

Total saving available

0.5%

The bank pays BR to Company A in exchange for 8.8% fixed, and accepts BR from Company B in exchange for paying it 8.6% fixed. The floating legs cancel inside the bank, which is left with 8.8% in and 8.6% out.

Company ABankCompany B8.8%BR8.6%BRborrows floatingat BR + 1%borrows fixedat 9%wants fixedends at 9.8%wants floatingends at BR + 0.4%the floating legs cancel;the bank keeps 0.2%Principal is never exchanged — only the interest flows are swapped.

Company A

Company B

Bank

Pays its own lender

BR + 1%

9%

—

Pays under the swap

8.8%

BR

BR + 8.6%

Receives under the swap

(BR)

(8.6%)

(BR + 8.8%)

Net

9.8% fixed

BR + 0.4%

0.2% earned

Cost of borrowing that way directly

10%

BR + 0.5%

—

Saving

0.2%

0.1%

—

The three amounts add back to the 0.5% that was available: 0.2% to A, 0.1% to B and 0.2% to the bank. The bank is paid for solving the matchmaking problem and for carrying the credit risk on both legs.

8.4 A method that works on any swap question

Five steps

  1. Write out the four rates in a two-by-two table and take the difference between the two spreads. That difference is the total gain available.

  2. Confirm it: total the cost if each party borrows what it wants, total it again if each borrows what it does not want, and take the difference.

  3. Decide the split — equally unless the question says otherwise — and write down the rate each party should end at.

  4. Work out the swap legs that produce those end rates, remembering that the floating legs must cancel.

  5. Check each party's net cost against what it could have done alone. If either is no better off, the legs are wrong.

8.5 What a swap does not do

  • The principal is never exchanged. Only the interest flows are swapped, on a notional amount, and neither party's own loan agreement changes. (A currency swap is different: because the two legs are in different currencies the principal is exchanged at both ends — chapter 9, section 10.)

  • It replaces interest rate risk with counterparty credit risk. If the other party fails, the entity is left with the borrowing it took out and none of the compensation it swapped for. Dealing through a bank moves that risk to the bank.

  • It does not repay anything early. A swap changes the character of the interest, not the maturity of the debt, which is why it is the standard tool for adjusting the interest basis of a debt portfolio without refinancing it — chapter 5, section 5, on the target debt profile.

9 Choosing an instrument

Binding?

Cost

Traded where

Best suited to

Smoothing and matching

n/a

None

Internal

Reducing exposure before any hedge is bought

Forward rate agreement

Yes

In the rate quoted

Over the counter

A single future borrowing or deposit of a known amount and date

Interest rate future

Yes

Small, but margin must be funded

Exchange

Larger exposures where a liquid contract exists

Interest rate option

No

A premium, paid up front

Either

Protecting against a rise while keeping the benefit of a fall, or where the borrowing may not happen

Cap, floor or collar

No (the bought leg)

A premium; much lower for a collar

Either

Shaping the exposure into a band over a longer period

Interest rate swap

Yes

The shared saving, less the bank's margin

Over the counter

Changing the interest basis of existing long-term debt

How to answer a "which instrument" question

Compute the outcome each available instrument produces, state each as a single figure on a common basis, and then recommend with a reason. The largest number is not automatically the answer: whether the underlying borrowing is certain to happen, whether the entity can fund a premium or a margin call, how long the exposure runs, and how much certainty the entity actually needs all bear on it.

Then say what the chosen hedge leaves uncovered — basis risk and the rounding on a futures hedge, the binding commitment on an FRA or a swap, the premium on an option in every outcome.

10 Test your knowledge

Two quick checks before you move on: work through the flashcards to fix this chapter’s terms and definitions, then sit the objective questions for exam-style practice. Both mark themselves and explain the answers as you go.

Practice questions

Interest Rate Risk Management

21 questions

Answer the questions one at a time. Your progress is saved so you can leave and come back.

Open chapter practice