Skip to contentSkip to search
Kaplan Publishing: Black Friday countdown

Washi Co - Sep 2018 Q1c(i)

Ggoh4h ago

Hi Sir John,

On the calculation for the additional debt finance needed, would the following be acceptable?

The examiner's answer calculated ARD/JPY and the final answer is different from mine.

JPY/ARD selling rate: 129.2/95.6 = 1.351

JPY/ARD buying rate: 132.4/92.7 = 1.428

Future buying rate in 1 year's time = 1.351 x (1.015/1.09) = 1.330 JPY/ARD

Project investment in JPY = 10,150,000,000 * 1.330 = 13,499,500,000

Additional debt required = 13,499,500,000 - 10,122,084,571 (receipt from treasury bills) = 3,377,415,429