Throughput accounting..

Rrosin5y ago
Hello sir, Sir I have conceptual doubt about bottleneck (process or resource) Would it be right to call bottleneck resource as the slowing process rather than slowest process. I.e should I determine the bottleneck by identifying the slowest process or should I take capacity also to consideration.. It may be a silly doubt sorry if though!
John MoffatJohn MoffatTutor5y ago#1
The bottleneck process is the process that is limited the number of units that can be produced - the process that is slowing everything else down. Have you watched my free lectures on this?