100 hours of unskilled labour, currently paid at $5.50 per hour, are needed for the contract. Z Co has no surplus capacity at the moment , but additional temporary staff could be hired at $6.50 per hour.
What is the relevant cost of the unskilled labour on the contract?
A $0
B $550
C $600
D $650
Ans: D
Sir why is the answer not B because that is a cheaper option for the firm($550 vs $650). Here we dont have contrn lost amount so we can ignore that and assume that the company will choose the cheaper option which is the cost of shifting unskilled labour($550). So how is that wrong?
Ask the Tutor ACCA PM
Study text Practice question
They have two choices if they do contract Z. One is to hire temporary staff to do the contract and this would cost $6.50 per hour.
The other choices is to move current labour (in which case still be paying them $5.50), but if they do that then they will have to hire temporary staff to do the current work, and that will cost $6.50 an hour.
So in either case they will end up having to pay $6.50 an hour for the 100 hours needed.
Have you watched my free lectures on relevant costing? The lectures are a complete free course for Paper PM and cover everything needed to be able to pass the exam well.