Skip to content
How did your June exams go?

Ask the Tutor ACCA PM

Study text Practice question

AAndy6y ago
100 hours of unskilled labour, currently paid at $5.50 per hour, are needed for the contract. Z Co has no surplus capacity at the moment , but additional temporary staff could be hired at $6.50 per hour. What is the relevant cost of the unskilled labour on the contract? A $0 B $550 C $600 D $650 Ans: D Sir why is the answer not B because that is a cheaper option for the firm($550 vs $650). Here we dont have contrn lost amount so we can ignore that and assume that the company will choose the cheaper option which is the cost of shifting unskilled labour($550). So how is that wrong?
John MoffatJohn MoffatTutor6y ago#1
They have two choices if they do contract Z. One is to hire temporary staff to do the contract and this would cost $6.50 per hour. The other choices is to move current labour (in which case still be paying them $5.50), but if they do that then they will have to hire temporary staff to do the current work, and that will cost $6.50 an hour. So in either case they will end up having to pay $6.50 an hour for the 100 hours needed. Have you watched my free lectures on relevant costing? The lectures are a complete free course for Paper PM and cover everything needed to be able to pass the exam well.
Sign into reply to this topic.