Forums›ACCA Forums›Standard cost cardACCA ForumsPMStandard cost cardAAndrew6y agoPlease can someone advise on below question What is labour cost per unit if 1st batch 90 hrs learning rate 80% learning ceases after 45 batches, labour paid at $20 per hour Any help appreciated Thank you Sign into reply to this topic.
AAndrew6y agoPlease can someone advise on below question What is labour cost per unit if 1st batch 90 hrs learning rate 80% learning ceases after 45 batches, labour paid at $20 per hour Any help appreciated Thank you