Shadow price?

((deleted)16y ago
will only shadow price of materials be asked or also will shadow price of labour be asked?
John MoffatJohn MoffatTutor16y ago#1
You can be asked for the shadow price of any limited resource. However the approach is always the same. Rewrite the constraint equation assuming one extra unit of the limited resource. Re-calculate the optimum/best mix and the new total contribution. The shadow price is the extra contribution.