Annual demand for raw material is 1,000,000 units. Each unit costs 15 cents. Procurement costs for each order are $20 and lead time has been estimated as 2 days. There are 250 working days per annum, the carrying cost of inventory is 10 cents per unit and the cost of a stock out is 20 cents per unit. What is the optimal reorder level? A 125 B 8,000 C 20,000 hi i dont know how to solve this question the formula for reorder level is maximum usage* maximum lead time in the kaplan textbook but in the answer this formula is not used can u please help me with thx
John MoffatJohn MoffatTutor3y ago#1
They need to reorder when they have enough inventory to last 2 days. They are using 1,000,000/250 = 4,000 units per day. Therefore the reorder level is 2 x 4,000 = 8,000.
Kkashaf3y ago#2
thx
John MoffatJohn MoffatTutor3y ago#3
You are welcome.