KKanan7y ago
Hi my dear tutor, i have a question. do we consider rental cost and lease pays as relevant cost or committed cost?
John MoffatJohn MoffatTutor7y ago#1
It depends on what the wording of the question is. If they are extra costs as a result of doing the new work, then they are relevant costs. If they are existing costs that do not change, then they are not relevant costs.