- This topic has 5 replies, 3 voices, and was last updated 9 years ago by .
Viewing 6 posts - 1 through 6 (of 6 total)
Viewing 6 posts - 1 through 6 (of 6 total)
- You must be logged in to reply to this topic.
Interactive BPP books for June 2026 exams, recommended by OpenTuition.
Get discount code >>
Forums › Ask ACCA Tutor Forums › Ask the Tutor ACCA PM Exams › Question Bank – Kaplan – Section B – BEFT CO – Q209 – P94
Hi John,
I was wondering if you could help me out here please.
In the Kaplan Question Bank – Section B – Question 209 – BEFT CO.
In solutions, some how they got 0.5 hours of painting and contribution of 30 per painting hour.
I am not sure how and where it is coming from.
Many Thanks
Jitin
I am sorry, but I only have the BPP Revision Kit and without seeing the whole question I cannot really help.
(If it is a past real exam question then I can help, but in that case please also say which exam date it was.)
Thanks John.
Dont think I can upload a picture somehow….!
Sorry, but no (and there would be copyright problems anyway) 🙁
hi i think i might know the solution @malikjitin.
Mr Moffat im sorry im commenting here as i didnt know how to message for this problem in the acca forum, directly addressing the recipient.
this is just one off sorry.
1. 0.5 hours of painting = 0.5 is the hours per limiting factor. in this question it is “painting labour” because this is limited .
therefore, to calculate the limiting hours for SQUARE
painting labour is $3 /$6= 0.5( this is cost per unit/labour rate per
week)
2.$30 is contribution per limiting factor= you calculate the contribution for SQUARE as normal
ie SP-Material-Labour-Variable overheads= contribution
39-6-11-7=15
therefore contribution per limiting factor is $15/0.5 hours=$30.
Numera,
Got it. Many Thanks for your help.
I am sure John would appreciate it as well.
Thanks again.
Jitin
