This is qs17 in bpp kit ..the answer requires pi to b calculated ..the profitability index is calculated as npv+ initial investment/ initial investment
But the answers for pi are different in kit if I use above formula .in each answer they are deduction the value from 1 ..why is that so ! Can't we prioritise the investments based on pi values itself !
For example for project po801 initial investment is 620000$ and npv is 55000$...the pi according to the formula above is ,1.088 but kit writes 0.0887 .....please clarify
Ask the Tutor ACCA AFM
Qs. Slow fashions co
The profitability index is usually defined as being the NPV / initial investment. However it can also be used as being NPV + initial investment / initial investment.
Unless specified by the question, you can calculate it either way,. Obviously the figure you arrive at will be different, but that does not matter - you still get the marks. And obviously the ranking of projects will be exactly the same whichever of the two measures you use.
Thank you
You are welcome :-)