Q17-MMC from BPP Revision KitForums › Ask ACCA Tutor Forums › Ask the Tutor ACCA AFM Exams › Q17-MMC from BPP Revision KitThis topic has 1 reply, 2 voices, and was last updated 3 years ago by John Moffat.Viewing 2 posts - 1 through 2 (of 2 total)AuthorPosts August 19, 2021 at 10:28 am #632081 dilnoza90ParticipantTopics: 9Replies: 7☆Dear Sir,I am a bit confused regarding not including $14m (7m from Y0 and 7m from Y1) in “Pe” when calculating “delay option”. Why only 35m of investment included?Thanks August 19, 2021 at 3:14 pm #632155 John MoffatKeymasterTopics: 57Replies: 54478☆☆☆☆☆That $14M is being paid whatever happens, for the development.The option is as to whether or not to delay the decision to produce and market the game for 2 years.AuthorPostsViewing 2 posts - 1 through 2 (of 2 total)You must be logged in to reply to this topic.Log In Username: Password: Keep me signed in Log In