Process Costing

EEphraim5y ago
"During the month Job A was completed. If Job A was for an order of 1,000 units. However, due to some faulty processing, a total of 1,100 units (including 100 spoiled units) was produced. The total cost incurred for Job A was $3,850. Normal spoilage was set at 4% of good units produced." With reference to the above question, do i take the total quantity as 1,000 or 1,100 units? Because if i take 1,100 as the total, then the normal spoilage is 44 instead of 40 using 4% as the standard in this question. Any clarification is helpful. Thank you
John MoffatJohn MoffatTutor5y ago#1
The question says that the normal spoilage is "4% of good units produced". Although 1,100 units were produced, that included 100 spoiled units, and so only the remaining 1,000 were 'good units'.