Process costingForums › Ask ACCA Tutor Forums › Ask the Tutor ACCA MA – FIA FMA › Process costingThis topic has 1 reply, 2 voices, and was last updated 3 years ago by John Moffat.Viewing 2 posts - 1 through 2 (of 2 total)AuthorPosts August 17, 2021 at 9:22 am #631810 Muskan558MemberTopics: 3Replies: 0☆In the process costing, how do we come to know whether the ‘closing work in process’ is include in the ‘units transfer to process’ Or not???? August 17, 2021 at 2:18 pm #631837 John MoffatKeymasterTopics: 57Replies: 54478☆☆☆☆☆If it is work-in-progress then it has not been transferred to the next process.Have you watched my free lectures on Process Costing? The lectures are a complete free course for Paper MA and cover everything needed to be able to pass the exam well.AuthorPostsViewing 2 posts - 1 through 2 (of 2 total)You must be logged in to reply to this topic.Log In Username: Password: Keep me signed in Log In