PLEASE ADVISEForums › ACCA Forums › ACCA PM Performance Management Forums › PLEASE ADVISEThis topic has 2 replies, 2 voices, and was last updated 9 years ago by ritesh1990.Viewing 3 posts - 1 through 3 (of 3 total)AuthorPosts November 7, 2014 at 12:46 pm #208228 ritesh1990ParticipantTopics: 2Replies: 3☆X AND Y PRODUCES WIDGET EACH SHOULD TAKE 0.5 HOURS TO MAKE. STANDARD RATE OF PAY IS $ 10 IDLE TIME TO BE 5% OF HOURS PAIDTHEY ACTUALLY PRODUCES 10800 WIDGET THEY PAY 6000 HOURS FOR $ 50000 OF WHICH 330 ARE IDLE TIMEWHAT IS LABOUR EFFICIENCY AND LABOUR IDLE TIME VARIANCE November 7, 2014 at 3:02 pm #208241 paulMemberTopics: 1Replies: 1☆Labour efficiency: std hr*actual pdn-actual hrs paid =(0.5*10800-6000)hrs remaining hrs less idle hrs, the multiply by std rate =(600hrs-330)10/95% =2842(A) November 8, 2014 at 7:52 pm #208483 ritesh1990ParticipantTopics: 2Replies: 3☆thanksAuthorPostsViewing 3 posts - 1 through 3 (of 3 total)You must be logged in to reply to this topic.Log In Username: Password: Keep me signed in Log In