sir in a question where we are asked to find planning and operational labor efficiency variances, if we are given both actual hours worked and actual hours paid for(paid idle time+actual hrs worked) then which figure do we take?
Many thanks!
Ask the Tutor ACCA PM
planning and operational efficiency variance
For all labour efficiency variances we take the hours worked.