Budget activity 50%. 75%
Budget overhead100000 112500
what would the budgeted overhead cost be for an activity level of 80%.?
Ask the Tutor ACCA MA
Overhead
There is no point in just setting test questions and expecting an answer - you must have an answer in the same book in which you found the question. Ask about whatever it is in the answer that you are not clear about and then I will help you.
You need to use the high-low method to calculated the fixed cost and the variable cost per %. The high low method is explained in my free lectures.
Hello , thanks for replying
The ans given is 115000
And I got it.
Thanks
You are welcome :-)