budgeted overhead for a period were 340000 for which actual labour hours and overhead were 21050 and 343825 respectively. if there was over absorbed of 14025, how many labour hours were budgeted?
information; budgeted actual production 8000units 9000units variable POH $3 $3 fixed POH $360000 $432000 sales 6000units 8000units
oerhead are absorbed using a rate per unit, based on bugeted output and expenditure?
I assume that you have an answer to the question in whichever book you found the question (and I assume that you have watched our free lectures because they are a complete course for Paper F2 and cover everything you need to pass the exam well).
If you say what your problem is then I will happily try and help you 🙂