operational labour efficiency varianceForums › Ask ACCA Tutor Forums › Ask the Tutor ACCA PM Exams › operational labour efficiency varianceThis topic has 3 replies, 2 voices, and was last updated 5 years ago by John Moffat.Viewing 4 posts - 1 through 4 (of 4 total)AuthorPosts May 22, 2019 at 1:25 pm #516857 maria16ParticipantTopics: 14Replies: 28☆how is the operational labour efficiency variance calculated without the revised time given in the question ? can we use the same standard time in the original budget? May 22, 2019 at 2:48 pm #516877 John MoffatKeymasterTopics: 57Replies: 54629☆☆☆☆☆If there is no revised time given then you assume that there is no revision and that the original standard time remains. May 22, 2019 at 3:14 pm #516884 maria16ParticipantTopics: 14Replies: 28☆oh right! exam stress has made me blind 🙂 thank you so much Mr. John! May 23, 2019 at 8:05 am #516960 John MoffatKeymasterTopics: 57Replies: 54629☆☆☆☆☆You are welcome 🙂AuthorPostsViewing 4 posts - 1 through 4 (of 4 total)The topic ‘operational labour efficiency variance’ is closed to new replies.