how is the operational labour efficiency variance calculated without the revised time given in the question ? can we use the same standard time in the original budget?
Ask the Tutor ACCA PM
operational labour efficiency variance
If there is no revised time given then you assume that there is no revision and that the original standard time remains.
oh right! exam stress has made me blind :) thank you so much Mr. John!
You are welcome :-)