NPvForums › Ask ACCA Tutor Forums › Ask the Tutor ACCA AFM Exams › NPvThis topic has 1 reply, 2 voices, and was last updated 10 years ago by John Moffat.Viewing 2 posts - 1 through 2 (of 2 total)AuthorPosts May 21, 2014 at 7:59 pm #169978 hasanali95MemberTopics: 239Replies: 248☆☆☆In the npv calculation,what do we do with the opportunity costs(of for e.g labor being unable to workon another project etc)? May 21, 2014 at 8:24 pm #169986 John MoffatKeymasterTopics: 57Replies: 54482☆☆☆☆☆Opportunity costs (i.e. lost income ) are treated just like direct costs. They are included in the cash flows.If you have a question that is causing you problems, then post the details and I will try and help.AuthorPostsViewing 2 posts - 1 through 2 (of 2 total)You must be logged in to reply to this topic.Log In Username: Password: Keep me signed in Log In