Hi, I have done 20 questions test on your website. There is a question about relevant costing, unfortunately I could not copy and paste it but I will describe it the best I can: The company has been offered a contract, which requires 5000 hrs of labour. The labour is currently working on another contract generating contribution of £12. There is lot of idle time, labour is paid £8 per hour. What is the relevant labour cost for the contract? I believe that cost should be zero as there is some spare capacity, which is an idle time. However the correct answer is £40,000. Please could you explain why?
John MoffatJohn MoffatTutor11y ago#1
Sorry, it is an error and the answer should be zero. The test has now been corrected. Thank you for pointing it out. (Incidentally, because the questions are selected at random from a large bank of questions, do try the test a few times - you are likely to get different questions each time :-) )