march/june 2016 Q4

((deleted)9y ago
Dear sir, How would the answer differ if the expected NPV of the strike price of USD15m had not been 0?
John MoffatJohn MoffatTutor9y ago#1
The current value (the PV of the future flows) would be higher by the amount of the NPV.