Machine set-up cost

HHinthu1y ago
A company manufactures memory chips for phones. A customer has ordered 300 chips. A standard batch of 100 chips has the following costs: Direct materials $25 Direct labour $10 Machine set up $100 The production overheads are $100 per labour hour. Labour is paid $20 per hour. What is the cost of this customer order? In the answer, the machine setup cost has been mentioned as $300$. Why has the machine setup been performed thrice? Since different products have not been produced, the machine setup should remain the same, shouldn't it?
John MoffatJohn MoffatAdmin1y ago#1
The costs are for batches of 100 chips, and the customer wants 300 chips. So they need to make 3 batches.
HHinthu1y ago#2
Okay, but given that they produce the same chips, wouldn't they need to reconfigure the machine ?
John MoffatJohn MoffatAdmin1y ago#3
Maybe not, but the question specifically says that $100 is the cost for a batch of 100 chips, and there are 3 batches.
HHinthu1y ago#4
Ok, Thank you
John MoffatJohn MoffatAdmin1y ago#5
You are welcome :-)