A company manufactures memory chips for phones. A customer has ordered 300 chips.
A standard batch of 100 chips has the following costs:
Direct materials
$25
Direct labour
$10
Machine set up
$100
The production overheads are $100 per labour hour. Labour is paid $20 per hour.
What is the cost of this customer order?
In the answer, the machine setup cost has been mentioned as $300$. Why has the machine setup been performed thrice? Since different products have not been produced, the machine setup should remain the same, shouldn't it?
Machine set-up cost
The costs are for batches of 100 chips, and the customer wants 300 chips. So they need to make 3 batches.
Okay, but given that they produce the same chips, wouldn't they need to reconfigure the machine ?
Maybe not, but the question specifically says that $100 is the cost for a batch of 100 chips, and there are 3 batches.
Ok, Thank you
You are welcome :-)