A manufacturing company wants to measure the learning rate that it has achieved with the manufacture of a new product item.The first item produced took 6 hours to make and the average time for the first 16 units was 3.3 hours.What has been the learning rate for this product? ( a bpp sec a question) Ans : 86%. Pls help sir.
John MoffatJohn MoffatAdmin10y ago#1
The fourth root of (3.3/6) = 0.86 (86%). It is using the doubling rule, and 16 is doubling 4 times. (If you watch the free lecture on learning curves then there is a full explanation of the doubling rule.)