If production first batch take 45 hours
Month Total batches produced to date. Actual learning curve
1 1
2 2 75 %
3 4 75 %
4 8 90%
I cannot find average production time per batch for the first eight bathes which is 22.78.
Hope tutor can help.
Ask the Tutor ACCA PM
Learning curve
Every time we double production, the average time falls to a % of the previous average time.
So if the first is 45, the average time per batch for 2 is 75% x 45
The average time if they make 4 is 75% x 75% x 45
The average time if they make 8 is 90% x 75% x 75% x 45 = 22.78
I do suggest that you watch the free lectures - they are a complete course covering everything you need to pass F5 well.
Thank you
You are welcome :-)