WWoon11y ago
If production first batch take 45 hours Month Total batches produced to date. Actual learning curve 1 1 2 2 75 % 3 4 75 % 4 8 90% I cannot find average production time per batch for the first eight bathes which is 22.78. Hope tutor can help.
John MoffatJohn MoffatTutor11y ago#1
Every time we double production, the average time falls to a % of the previous average time. So if the first is 45, the average time per batch for 2 is 75% x 45 The average time if they make 4 is 75% x 75% x 45 The average time if they make 8 is 90% x 75% x 75% x 45 = 22.78 I do suggest that you watch the free lectures - they are a complete course covering everything you need to pass F5 well.
WWoon11y ago#2
Thank you