This is from the Revision Mock Exam Y plc produces widgets Each widget takes 0.5 hours to make. The standard rate of pay is $10 per hour. Idle time is expected to be 5% of hours paid. They actually produce 10,800 units. They pay $50,000 for 6000 hours, of which 330 hours are idle. What is the labour efficiency variance? Answer - $2,842 A
John MoffatJohn MoffatTutor11y ago#1
So? What is your question? (The answer is correct if that is what you are asking!)
MMarianne11y ago#2
I couldn't understand how they got the answer, but I see you now answered it on someone elses thread. Thanks