In the last period an organisation budgeted to work 116,000 hours manufacturing 29,000 units. Actual output last period was 26,000 units which took 108,000 hours to manufacture
the formula to get the labour efficiency ratio is
standard hrs for actual output/actual hrs worked x 100so; 26,000 units x 116,000hours = 3,016,000,000/108,000×100
im supposed to get the answer by percentage but what im getting is 27,925.9why is it like that?
June 12, 2016 at 1:01 pm #322555Why on earth do you want to multiply 26,000 by 116,000? The question does not say that they took 116,000 hours each – that would be ridiculous – they take 116,000 hours in total.
(If they took 116,000 hours for each unit, it would mean they were taking over 13 years to produce one unit 🙂 )
June 20, 2016 at 6:31 am #323537i am confused, how do you get the answer then?
June 20, 2016 at 6:52 am #323542standard hours per unit = 116,000 / 29,000
Therefore standard hours for actual output = 26,000 x 116,000/29,000 = 104,000
Actual hours worked = 108,000Now you can use the formula that you typed before.