Skip to content

Ask the Tutor ACCA PM

Key factor analysis

MMichael8y ago
Good afternoon. I would like to ask if it is always necessary to divide the contribution with the hours per unit. Why do we mind that? We do the same even if the limited resource isn't the available hours? I am exempted from F2. Thank you very much. :)
John MoffatJohn MoffatTutor8y ago#1
We divide the contribution by whatever the limiting factor is - usually it is hours but if it was (for example) materials then we divide by the materials required per unit.
Sign into reply to this topic.