Forums › Ask ACCA Tutor Forums › Ask the Tutor ACCA AFM Exams › June 2010-Q1
- This topic has 3 replies, 2 voices, and was last updated 10 years ago by John Moffat.
- AuthorPosts
- May 28, 2014 at 6:20 am #171343
Hi John,
I would like to know why the discount factor for 2012 is 0.909 instead of 1? I thought the construction is commencing in Jan 2012 and it didn’t say that the costs will only incur at the end of the year.
Thank you.
May 30, 2014 at 10:04 am #171851You are correct – the question does not say end of year, and it is an assumption (as always with P4, there is hardly ever one ‘correct’ answer – it depends (as in real life) on what assumptions are made.
The assumption here is actually a sensible one. Since we are constructing (as opposed to simply paying for a machine or whatever) it is likely that the costs will be incurred throughout the year (rather than as just one lump sum for the year). So they have been treated in the same way as we treat operating costs – i.e. assumed they occur at the end of the year (because discounting if they were spread throughout the year would be over-complicated).
May 30, 2014 at 5:25 pm #171960Thank you John!
May 30, 2014 at 5:54 pm #171965You are welcome 🙂
- AuthorPosts
- You must be logged in to reply to this topic.