- This topic has 3 replies, 2 voices, and was last updated 4 years ago by .
Viewing 4 posts - 1 through 4 (of 4 total)
Viewing 4 posts - 1 through 4 (of 4 total)
- The topic ‘Idle Time question’ is closed to new replies.
Interactive BPP books for June 2026 exams, recommended by OpenTuition.
Get discount code >>
Forums › Ask ACCA Tutor Forums › Ask the Tutor ACCA MA – FIA FMA › Idle Time question
Budgeted production in a factory for next period is 4800 units. Each unit requires five labour hours to make. Labour is paid $10 per hour. Idle time represents 20% of the total labour time.
What is the budgeted total labour cost for the next period?
I did this question and got $288000 as the answer, but I am not sure if it is correct.
Why are you attempting a question for which you do not have an answer? You should be using a Revision Kit from one of the ACCA Approved Publishers – they have answers and workings 🙂
Your answer is not correct.
If 20% of the total time is idle, then only 80% of the time paid for is used to actually make the units.
They will be working 4,800 x 5 = 24,000 hours and therefore they will have to pay for 24,000/80% = 30,000 hours. (And it checks – 20% x 30,000 = 6,000 hours idle, leaving 24,000 hours worked).
Therefore the total labour cost is 30,000 hours x $10 per hour = $300,000.
Thank you for the explanation Sir, I understand my mistake now. This question was from a mock exam that’s why there wasn’t an answer for the question.
You are welcome.
