Hi Sir John,
On the Value at Risk analysis, is the mean / expected NPV of the project the value calculated in part (ii) which is $1,888,000 [APV] ?
If yes, would this mean that since the VaR is $3,619m, at the 95% threshold, the project's APV has fall below zero?