I Wanted to know if there is any planning and operational variance formula for fixed overhead varaiane i.e the fixed overhead expenditure & fixed overhead volume variance (fixed overhead efficiency and fixed overhead capacity variance).
Ask the Tutor ACCA PM
formulas of planning and operational fixed overhead variance
No - the exam does not ask planning and operational variances for fixed overheads. (and you should not just learn formulae anyway - the exam deliberately tests that you understand what it happening)
What is covered in the my free lectures is what is needed for the exam.